Copy of results from one inspection lot to another lot

$
0
0


Dear Gurus

 

A solution  is needed for  the secnario described below.

 

    Quality inspection lot origin 04 is created when our production worksheet gets confirmed.

   The materials are consumed thru backflushing with movement type 261.This is a zdevelopment.

   The production supervisor commits some mistake while entering which is identified later, the reason

   being wrong production version, or wrong material entered.

   Meanwhile the quality personnel has entered their test results against each MIC of the material having

   different batch nos in the inspection lot.

   To rectify the error , the production supervisor will be creating a new worksheet    with the correct entry

   and confirms the  worksheet , triggering creation of another new inspection lot.

  The quality people doesn't want to  re-enter the results in the new inspection lot if the material is same

  They want all the results of the old   inspection lot to be copied onto the new inspection lot against each batch.

  The old worksheet is cancelled and the material consumption are withdrawn with  movement type 262

 

   The results of th inspection lot(wrong)  should be copied to the new inspection lot created only when the users    comes   across this situation.

   tried doing it , but not able to succeed , because for each inspection lot entry, it is asking for the

  source inspection lot, and the results are not getting copied.

 

   Is there any way to do this only when required for copying.

 

  Pls help.

 

  Regards

  Vidhyadharan