Hello all,
Need your guidance again.
The planned order's generated from the Planning table are created with order type PE(Run Schedule Quantity), whereas the ones that are generated (through MRP run) from the requirements via Demand Management are defaulted to order type : LA.
Note:
1. REM indicator is activated and a valid REM profile is maintained as well.
2. Prod version is allowed with REM.
3. Necessary Scheduling Parameters are defined in OPU5.
what do i miss here ?
Please do help me out.
Regards,
Rahul